The first floor of the student commons takes shape as the preliminary
foundation work was recently completed.
Throughout February and into March, piles were driven into the soil to provide foundational support for the structure, and to allow for the installation of various below-grade utility services including functional spaces for storage, mechanical/electrical rooms and crawlspaces.
In April, the crew encountered heavy rock conditions along the west side of the building site, which required the use of a specialized drilling rig to complete the subterranean foundation.
Throughout February and into March, piles were driven into the soil to provide foundational support for the structure, and to allow for the installation of various below-grade utility services including functional spaces for storage, mechanical/electrical rooms and crawlspaces.
In April, the crew encountered heavy rock conditions along the west side of the building site, which required the use of a specialized drilling rig to complete the subterranean foundation.
The ground floor began to take shape with the pouring of the
first concrete slab on May 17. This work continued throughout May and into June
while the west retaining wall along Waldo Avenue was erected. The final ground
floor section was poured on June 12.
Throughout the coming weeks, the west retaining wall will be
completed and concrete columns and floor slabs will rise to the roof level.
The last section of the first floor was poured on June 12. |